Preparing production space for the new battery line in Halls W1/W2.

Team Montage began in April 2023 in Hall W1 with the dismantling of the Panther Supercubing Module D equipment for transportation and reuse in Halewood for the Flash project. This was followed by preparing the space by clearing out offices and associated functions, as well as refurbishing the floor structure and painting the roof in preparation for installing the new battery production line.

Simultaneously, Team Montage cleared the space related to Fox production in Hall W2. This involved demolishing existing floorings, demolishing existing utility buildings in the hall, refurbishing floors with reinforcement, concrete, and finishing with epoxy paint. Additionally, the existing metal structure was cleaned and repainted, refurbishments were made to fire extinguishing and lighting installations, and electrical supplies were installed for the robots of the new battery production line. To date, over 60,200 work hours have been recorded on all projects, with no lost time incidents (LTCR).

Client: Automotive industry company with production facilities in Craiova
Type of works: Construction assembly and Dismantling/assembly of equipment
Location: Cologne, Germania
Duration: 04.2023 - 05.2024
Budget: 7.800.000 €